Time and Work — Short Notes

⭐ Important points upar highlighted hain — pehle wo padho, phir detail me samjho, aakhir me practice karo.

⭐ Sabse Important Points · एक नज़र में

  • Work Rate: If A finishes work in x days, A's one-day work = 1/x.
  • Efficiency Ratio: If A is k times as efficient as B, then time taken by A = (1/k) times time taken by B.
  • Combined Work: If A and B work together, their one-day work = 1/x + 1/y, and time taken = xy/(x+y) days.
  • Wage Distribution: Wages are proportional to work done (or efficiency) when working for the same time.
  • Efficiency and Time: Efficiency is inversely proportional to time taken. If efficiency ratio is a:b, time ratio is b:a.
  • LCM Method: Let total work = LCM of days. Efficiency = Total work / Days. Then solve using integer values.

Introduction · परिचय

Time and Work is a core arithmetic topic in RRB Group D Mathematics. It deals with the rate at which individuals or groups complete a task, and how their combined efforts affect the total time taken. Mastering this topic helps solve problems quickly using unitary methods, efficiency ratios, and LCM-based shortcuts.

Basic Concepts and Unitary Method

If a person can complete a work in 'n' days, then the work done by that person in one day is 1/n. Conversely, if a person does 1/n work in one day, the total time taken to finish the work is n days. When multiple people work together, their one-day work rates are added. The total work is always taken as 1 unit unless specified otherwise.

📐 Formula / Rule Box · सूत्र याद रखो

Combined Work Time

Time = xy/(x+y) days

One-day Work

Work done in 1 day = 1/n

⭐ Key Points · याद रखने वाली बातें

  • Work Rate: If A finishes work in x days, A's one-day work = 1/x.
  • Combined Work: If A and B work together, their one-day work = 1/x + 1/y, and time taken = xy/(x+y) days.
  • Efficiency and Time: Efficiency is inversely proportional to time taken. If efficiency ratio is a:b, time ratio is b:a.

✍️ Solved Example 1 · हल किया हुआ उदाहरण

❓ Question: A can do a piece of work in 10 days and B can do it in 15 days. How long will they take to finish it together?

✅ Solution: 6 days

💡 Explanation: A's one-day work = 1/10, B's one-day work = 1/15. Combined one-day work = 1/10 + 1/15 = (3+2)/30 = 5/30 = 1/6. So, together they finish in 6 days.

Efficiency, Wages, and LCM Method

Efficiency is the rate of doing work. If A is twice as efficient as B, A takes half the time B takes. Wages are distributed in proportion to work done or efficiency. The LCM method simplifies calculations: take total work as LCM of given days, then find individual efficiencies (work per day). This avoids fractions and speeds up solving.

📐 Formula / Rule Box · सूत्र याद रखो

Efficiency Ratio

Efficiency ∝ 1/Time

Wage Share

Wage ∝ Work done

⚖️ Comparison · अंतर साफ-साफ
Unitary MethodLCM Method
Uses fractions (1/x)Uses whole numbers
Slower for complex problemsFaster and less error-prone
Good for simple two-person problemsGood for multiple workers and efficiency problems

⭐ Key Points · याद रखने वाली बातें

  • Efficiency Ratio: If A is k times as efficient as B, then time taken by A = (1/k) times time taken by B.
  • Wage Distribution: Wages are proportional to work done (or efficiency) when working for the same time.
  • LCM Method: Let total work = LCM of days. Efficiency = Total work / Days. Then solve using integer values.

✍️ Solved Example 1 · हल किया हुआ उदाहरण

❓ Question: A is twice as efficient as B. Together they finish a work in 8 days. How long would B alone take?

✅ Solution: 24 days

💡 Explanation: Let B's efficiency = 1 unit/day, then A's efficiency = 2 units/day. Combined efficiency = 3 units/day. Total work = 3 × 8 = 24 units. B alone takes 24/1 = 24 days.

Practice Questions · खुद हल करके देखो

पहले खुद try karo, phir “Answer dekho” dabakar check karo. 👇

Q1A can complete a work in 12 days and B in 18 days. They work together for 4 days, then A leaves. How many days will B take to finish the remaining work?

👀 Answer dekho

✅ Answer: 8 days

💡 Explanation: A's rate = 1/12, B's rate = 1/18. Combined rate = 1/12 + 1/18 = 5/36. Work done in 4 days = 4 × 5/36 = 20/36 = 5/9. Remaining work = 4/9. B alone does 1/18 per day, so time = (4/9) / (1/18) = 8 days.

Q2If 6 men can do a work in 8 days, how many men are needed to do the same work in 4 days?

👀 Answer dekho

✅ Answer: 12 men

💡 Explanation: Total work = 6 × 8 = 48 man-days. To finish in 4 days, men required = 48/4 = 12.

Q3A and B together can do a work in 10 days. A alone can do it in 15 days. In how many days can B alone do it?

👀 Answer dekho

✅ Answer: 30 days

💡 Explanation: Combined rate = 1/10, A's rate = 1/15. B's rate = 1/10 - 1/15 = (3-2)/30 = 1/30. So B alone takes 30 days.

⚠️ Common Mistakes · ये गलतियाँ बिल्कुल मत करना

  • Adding times instead of rates: Always add one-day work (1/x + 1/y), not x + y.
  • Forgetting to convert efficiency ratio to time ratio: If efficiency ratio is a:b, time ratio is b:a.
  • Ignoring units: Ensure all times are in the same unit (days, hours) before calculating.

⚡ Quick Revision · Exam से पहले 2 मिनट में दोहराओ

  • Work Rate: One-day work = 1/n if work finishes in n days.
  • Combined Work Formula: For two persons, time = xy/(x+y) days.
  • LCM Method: Take total work as LCM of days, then efficiency = total work / days.
  • Efficiency vs Time: Efficiency is inversely proportional to time taken.
  • Wage Rule: Wages are shared in proportion to work done (efficiency × time).